Schooner Creek Discovery Park Development

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

 


12.14.2024 SCDP Playground Opening & Ribbon Cutting

The new Schooner Creek Discovery Park is located at 4815 SE 51st Street, Lincoln City, OR 97367.

As of Summer 2024, we are in Phase 1 of the 3 Phased Park Project. Phase 1 construction broke ground on June 20th, with a well-attended Groundbreaking Celebration. Phase 1 is expected to complete by the end of Fall 2024, with the 1st new inclusive and accessible playground on the Oregon Coast being opened to the public. What is an Inclusive Playground vs an Accessible Playground? Please see here: Inclusive vs Accessible   

Want to support the new park? Click here to DONATE

To fund a paver, bench or other amenity for the new Park, click here to:  COMMEMORATE

Want to order a Schooner Creek Discovery Park Commemorative Item? Click here for a PDF order form below.

 This project has been funded in part by a grant from Travel Oregon.

TO_Primary_MossGreen_DeepBlue_RGB

 


 

Final park design revealed at 'Party in the Park' event on 8/29/23.

Final Design of New Park
We hosted six (6) public community events.

application/pdfCommunity Park in Taft - Public Process Schedule

The development and construction of the new Schooner Creek Discovery Park is stated as the #1 goal of the 2016 Lincoln City Parks System Plan, and will address a recreation gap in the southern part in the City.

In December 2020, Lincoln City was able to purchase the land from LCSD.

Thank you to the following for the current funding in place for start of construction:

  • $1 million from State Bill 5202 – Rep. Gomberg and Senator Anderson
  • $1.75 million grant funding – Oregon Parks and Rec Dept
  • $485k donation  - William Byrd Upjohn estate
  • $100k grant funding - Travel Oregon
  • $50k grant funding- Reser Family Foundation
  • $32k for musical instruments - Christmas Cottage of Lincoln City
  • $25k - Ford Family Foundation
  • $15k grant funding -  Lincoln County Community and Economic Development
  • $10k grant funding - Siletz Tribal Charitable Contribution Fund
  • $10k grant funding - Friends of Lincoln City Parks & Recreation and Roundhouse Foundation
  • $2k for 'World's Shortest Trail' - Oregon Parks Foundation
  • $5k grant funding - Friends of LCP&R and Marie Lamfrom
  • $3k grant funding - Pacific Power Foundation
  • Total: $3,487,000.00

Schooner Creek Discovery Park Press Releases

Park Development (FY20-21):

  • Acquisition of land from LCSD: $421,917
  • Phase I and II Environmental Survey Assessments

Park Development (FY21-22):

  • Exploratory survey
  • Topo and boundary survey
  • Building demolition
  • Conceptual design

Park Development (FY22-23):

  • Landscape architect for final design
  • Wetland delineation
  • Restroom architect
  • Lighting

Park Development (FY23-24):

  • Break ground on playground Summer/Fall 2024.
  • Public process for final park design completed.

Park Development Ongoing

  • Multi-use astro turf fields, covered multi-use court and special event area, outdoor sports courts, playground, picnic shelters, restrooms and more.

For more info, please contact Director Jeanne Sprague at jsprague@lincolncity.org or 541.996.1222.

 Overview of the Property / Future site of fields and event shelter

Schooner Creek Discovery Park Photo Gallery